Rolling up resources in MS Project

Question:

How do I see the effort (work) by resource at a summary task? See the example below

*Summary task

* Child task 1 (4 hs of of PM and 6 hs of a BA)
* Child task 2 (7 hs of of PM and 7 hs of a BA)

I would to see the following information:

* Summary task (11 hs of a PM and 13 hs of a BA)

Answer:

1. Create the scenario:

clip_image002

2. Switch to Resource Usage View:

clip_image004

3. Click on >Project, >Group By, >Customize Group by:

4. Check: Group assignments, not resources

5. Input Task Summary Name as the first Field Name, then select Assignment under field Type.

6. Input Name as the second Field Name.

clip_image006

7. Click on OK

Result:

clip_image008

Desired Result:

Summary task (11 hs of a PM and 13 hs of a BA)