    Rolling up resources in MS Project

    Question:

    How do I see the effort (work) by resource at a summary task? See the example below

    *Summary task

    * Child task 1 (4 hs of of PM and 6 hs of a BA)
    * Child task 2 (7 hs of of PM and 7 hs of a BA)

    I would to see the following information:

    * Summary task (11 hs of a PM and 13 hs of a BA)

    Answer:

    1. Create the scenario:

    clip_image002

    2. Switch to Resource Usage View:

    clip_image004

    3. Click on >Project, >Group By, >Customize Group by:

    4. Check: Group assignments, not resources

    5. Input Task Summary Name as the first Field Name, then select Assignment under field Type.

    6. Input Name as the second Field Name.

    clip_image006

    7. Click on OK

    Result:

    clip_image008

    Desired Result:

    Summary task (11 hs of a PM and 13 hs of a BA)

    评论

    请稍候...
    很抱歉,您输入的评论太长。请缩短您的评论。
    您没有输入任何内容,请重试。
    很抱歉,我们当前无法添加您的评论。请稍后重试。
    若要添加评论,需要您的家长授予您相应权限。请求权限
    您的家长禁用了评论功能。
    很抱歉,我们当前无法删除您的评论。请稍后重试。
    您已超过了一天之内允许提供的评论数上限。请在 24 小时后重试。
    因为我们的系统表明您可能在向其他用户提供垃圾评论,您的帐户已禁用了评论功能。如果您认为我们错误地禁用了您的帐户,请联系 Windows Live 支持部门
    完成下面的安全检查,您提供评论的过程才能完成。
    您在安全检查中键入的字符必须与图片或音频中的字符一致。
    Rich 在此页禁用了评论功能。

    引用通告

    此日志的引用通告 URL 是:
    http://pmconnection.spaces.live.com/blog/cns!501C1C457A6A99CA!995.trak
    引用此项的网络日志